Processes PMP Rita (Subject) / Alle Prozesse (Lesson)

Initiating, Planning, Monitoring & Controlling, Executing, Closing

This lesson was created by deb00330.

Learn lesson

Advertisement
  • Facilitate conflict resolution Executing
  • Send and receive information Executing
  • Hold meetings Executing
  • Select sellers Executing
  • Take action to control the project MC
  • Measure performance against the performance measurement baseline MC
  • Measure performance against other metrics determined by the project manager MC
  • Determine variances and if they warrant a change request MC
  • Influence the factors that cause changes MC
  • Request changes MC
  • Advertisement
  • Perform integrated change control MC
  • Approve or reject changes MC
  • Inform stakeholders of approved changes MC
  • Manage configuration MC
  • Create forecasts MC
  • Gain acceptance of interim deliverables from customer MC
  • Perform quality control MC
  • Report on project performance MC
  • Perform risk audits MC
  • Manage reserves MC
  • Administer procurements MC
  • Confirm work is done to requirements Closing
  • Complete procurement closure Closing
  • Gain formal acceptance of the project Closing
  • Complete final performance reporting Closing
  • Index and archive records Closing
  • Update lessons learned knowledge base Closing
  • Hand of completed product Closing
  • Release resources Closing