PMP (Subject) / PMP V4 Formeln (Lesson)

Formeln aus dem PMP Book v4

This lesson was created by Micmueller.

Learn lesson

Advertisement
  • PV Planned Value
  • EV Earned Value
  • AC Actual Cost
  • BAC Budget a Completion
  • EAC Estimate at completion
  • ETC Estimate to Completion    EAC-AC
  • VAC Variance at Completion   BAC-EAC
  • PERT expected activity duration (EAD) (P+4M+O)/6   Time Management
  • Standard deviation of an Activity (SD) (P-O)/6   Time Management
  • Variance of an activity "(P-O)/6" zum Quadrat
  • Advertisement
  • Range of an activity duration EAD +/- SD   Time Management
  • Total Float LS-ES, or LF-EF   Time M.
  • CV Formel EV - AC   Cost M.
  • SV Formel EV-PV   Cost M.
  • Cost Performance Index (CPI) EV/AC Cost.
  • Schedule Performance Index (SPI) EV/PV   Cost M.
  • To Complete Performance Index (TCPI) (BAC-EV)/(BAC-AC)   Cost. M.
  • Variance at Completion (VAC) BAC-EAC   Cost. P.
  • Communication Channels (N*(N-1))/2   Comm. M.
  • Expected Monetary Value (EMV) EMP = P x I   Rist Mangmt.
  • Point of Total Assumption (PTA) ((Ceiling Price - Target Price) / Buyer's share ratio) + Target costs   Procure. Mngmt