- PV Planned Value
- EV Earned Value
- AC Actual Cost
- BAC Budget a Completion
- EAC Estimate at completion
- ETC Estimate to Completion EAC-AC
- VAC Variance at Completion BAC-EAC
- PERT expected activity duration (EAD) (P+4M+O)/6 Time Management
- Standard deviation of an Activity (SD) (P-O)/6 Time Management
- Variance of an activity "(P-O)/6" zum Quadrat
- Anzeige
- Range of an activity duration EAD +/- SD Time Management
- Total Float LS-ES, or LF-EF Time M.
- CV Formel EV - AC Cost M.
- SV Formel EV-PV Cost M.
- Cost Performance Index (CPI) EV/AC Cost.
- Schedule Performance Index (SPI) EV/PV Cost M.
- To Complete Performance Index (TCPI) (BAC-EV)/(BAC-AC) Cost. M.
- Variance at Completion (VAC) BAC-EAC Cost. P.
- Communication Channels (N*(N-1))/2 Comm. M.
- Expected Monetary Value (EMV) EMP = P x I Rist Mangmt.
- Point of Total Assumption (PTA) ((Ceiling Price - Target Price) / Buyer's share ratio) + Target costs Procure. Mngmt