- outputs of monitor stakeholder engagement - work performance information - change requests - resource management plan (project management plan updates) - communications management plan (project management plan updates) - stakeholder engagement plan (project management plan updates) - issue log (project documents updates) - lessons learned register (project documents updates) - risk register (project documents updates) - stakeholder register (project documents updates)
- Constructive Changes contract changes which results in win win situations
- PTA point of total assumption PTA = ((Ceiling Price - Target Price)/buyer's Share Ratio) + Target Cost
- Geert Hofstede cultural dimension of individualism refers to the significance of the person versus that of the group.
- CSOW Contracted statement of work Statement of work part of contract
- Crashing Make plan faster by adding more resources or money (cash)
- Validate scope Ensure that everything has been delivered, what should have been delivered
- Total float Number of days a activity can be delayed. If activity is part of the critical path 0 days
- planning package Planning element between control accounts and work packages (tasks), some kind of user story between features and tasks
- communiation channels calculation (number of people * (number of people - 1)) / 2 5 member = (5 * 4)/ 2 = 10 7 member = (7 * 6)/ 2 = 21
- Advertisement
- contingency plan Is a plan B